NYCServers - NYC - Scheduled Power Maintenance - Single Cabinet – Maintenance details
All systems operational
NYC - Scheduled Power Maintenance - Single Cabinet
Completed
Scheduled for February 28, 2025 at 11:00 PM – March 01, 2025 at 5:00 AM
Affects
NYC Datacenter
Under maintenance from 11:00 PM to 5:00 AM
Updates
Completed
March 01, 2025 at 5:00 AM
Completed
March 01, 2025 at 5:00 AM
Maintenance has completed successfully
In progress
February 28, 2025 at 11:00 PM
In progress
February 28, 2025 at 11:00 PM
Maintenance is now in progress
Planned
February 28, 2025 at 11:00 PM
Planned
February 28, 2025 at 11:00 PM
On February 28, 2025 we will be performing power maintenance on one of our NYC datacenter cabinets. This will effect a small set of customers in our NYC location. An email will be sent to affected customers, as well as information posted below.
We will use this notification to post updates about the maintenance, as well as send an email notification at the conclusion of the maintenance window.
===========================================
Dear Valued Client,
We are writing to inform you of scheduled power maintenance that will affect your service. This maintenance is necessary to ensure the continued reliability and performance of our infrastructure.
Maintenance Details:
Date: February 28, 2025
Start Time: 6:00 PM EST
Expected Completion: 12:00 AM EST (Midnight)
Impact: Your service will be unavailable during this maintenance window
What to Expect:
We will begin the controlled shutdown of servers at 6:00 PM EST (after forex market hours)
All affected servers will be powered down during the maintenance
Services will be restored as soon as maintenance is complete
We anticipate full service restoration by midnight EST or earlier.
Recommended Actions:
Plan for system unavailability during the maintenance window; 6PM EST - 12:00AM EST Feb 28, 2025.